TEPCO has reported at 06:00:00 p.m. Saturday March 12, Eastern Time
Below is major impact to TEPCO's facilities due to the Miyagiken-Oki
*new items are underlined
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to earthquake
* The national government has instructed evacuation for those local
residents within 20km radius of the site periphery.
* High Pressure Coolant Injection System of Unit 3 automatically stopped.
We endeavored to restart the Reactor Core Isolation Cooling System but
failed. Also, we could not confirm the water inflow of Emergency Core
Cooling System. As such, we decided at 5.10AM, Mar 12, and we reported
and/or noticed the government agencies concerned to apply the clause 1 of
the Article 15 of the Radiation Disaster Measure at 5:58AM, Mar 13.
In order to fully secure safety, we operated the vent valve to reduce the
pressure of the reactor containment vessels (partial release of air
containing radioactive materials) and completed the procedure at 8:41AM,
Mar 13,
* We continue endeavoring to secure the safety that all we can do and
monitoring the periphery.
Comments