At 5:30 EDT, the NEI said that TEPCO reported at 3:00 p.m. EDT that work had resumed to pump seawater into Fukushima Daiichi 2 to maintain safe cooling water levels after the utility was able to vent steam from the pressure vessel. The fuel had been exposed for 140 minutes Monday night due to a malfunctioning pressure relief valve. Water levels later went up to cover more than half of the rods.
The U.S. Nuclear Regulatory Commission reports that the Japanese government has formally asked for assistance from the United States on nuclear power plant cooling issues triggered by the March 11 tsunami.
The agency has already sent two experts on boiling water reactor issues to Japan as part of a U.S. Agency for International Development disaster relief team. The experts now are in Tokyo providing technical assistance. The U.S. NRC is also monitoring the Japanese reactor events around the clock from its headquarters operations center in Rockville, Md.